Skip to content
  • Categories
  • Recent
  • Tags
  • Popular
  • World
  • Users
  • Groups
Skins
  • Light
  • Brite
  • Cerulean
  • Cosmo
  • Flatly
  • Journal
  • Litera
  • Lumen
  • Lux
  • Materia
  • Minty
  • Morph
  • Pulse
  • Sandstone
  • Simplex
  • Sketchy
  • Spacelab
  • United
  • Yeti
  • Zephyr
  • Dark
  • Cyborg
  • Darkly
  • Quartz
  • Slate
  • Solar
  • Superhero
  • Vapor

  • Default (Cyborg)
  • No Skin
Collapse
Brand Logo

CIRCLE WITH A DOT

  1. Home
  2. Uncategorized
  3. There's a lot of stuff going around about datacenters, so I decided to do a quick tour yesterday of some of the datacenters in the Salt Lake Valley.

There's a lot of stuff going around about datacenters, so I decided to do a quick tour yesterday of some of the datacenters in the Salt Lake Valley.

Scheduled Pinned Locked Moved Uncategorized
slc
71 Posts 32 Posters 3 Views
  • Oldest to Newest
  • Newest to Oldest
  • Most Votes
Reply
  • Reply as topic
Log in to reply
This topic has been deleted. Only users with topic management privileges can see it.
  • ricci@discuss.systemsR ricci@discuss.systems

    Next, an even smaller datacenter, that just about anyone in #SLC has seen! This is XMission, a local Internet Service Provider that's been running since 1993, so one of The Ancients in Internet time. It's on a very busy part of 4th South, and if you've been by at night, you've seen the big LED display on the front of the building that they put various animations on.

    One of the things that I *think* is probably in this building is SLIX: https://slix.net/traffic/ - this is an Internet Exchange Point (IXP), where various carriers meet up to exchange traffic without it having to travel long distances. These are often run as a sort of community infrastructure - it's in the best interests of all networks involved to connect to each other so that they can do their jobs more efficiently.

    SLIX is fairly small (according to their own data they carry ~200Gbps, with some spikes up to 1Tbps). There are about 40 networks that meet there: https://slix.net/participants/ . Funny story, when I first got Google Fiber at my house, I was getting routed through California to get to the University of Utah campus just a few miles away. I pinged a guy I know who pinged a guy he knows who ... learned that some of the participants in SLIX didn't have their routes set up right. A config change later, and not only me, but basically everyone on any commercial ISP in the Salt Lake Valley had much more direct routes to campus!

    ricci@discuss.systemsR This user is from outside of this forum
    ricci@discuss.systemsR This user is from outside of this forum
    ricci@discuss.systems
    wrote last edited by
    #3

    This one is larger, physically (22.5 sq ft), than the first datacenter we looked it, but claims less power: 490kw. That's not a ton of power - my Chevy Bolt can draw 150kw from its batteries at max acceleration, and there are much bigger and sportier EVs that can draw something almost up in the range of this datacenter! (though only for brief periods of course! this datacenter probably draws a substantial fraction that much 24/7) Why is there so much less power for this datacenter?

    Well, one of the key factors of datacenters is how power-dense they are: how much power they are designed to deliver to each rack, and how much heat they are capable of moving out.

    Compute - especially GPU compute for AI - is incredibly power-dense and incredibly hot. So we can guess this datacenter is probably not for compute. If I had to guess, this is probably mainly intended as a "carrier hotel" - it's probably focused on having telecoms companies as tenants. I base this both on the lower power density, and where it is: it's near the Utah State Fairpark, which is in turn relatively close to train tracks heading both east-west and north-south. A lot of long-distance fiber in the US follows both the rail and Interstate road networks, because it's relatively straightforward to run fiber alongside transportation links. Salt Lake City lies on the west side of some of the few passes through the Rockies, so it has a ton of fiber, following I-80, the Union Pacific, etc. This is a good place for carrier hotels.

    How is a carrier hotel different from an IXP? At an IXP, the carrier is just pulling in some fiber, maybe one or two routers or something. But they have a lot more equipment that they need than that - they have servers of various kinds too, plus the bigger backbone routers that fan out in many directions, etc. Mobile carriers have a fair amount of wired topology to deal with. That's the kind of stuff they put in carrier hotels, and this is a good spot for them.

    I picked this shot because, in the background, you can see the Gadsby Power Plant, one of the main sources for power in #SLC. That's a natural gas plant that generates about 300MW. Put a pin in that number, we'll come back to it later.

    Link Preview Image
    ricci@discuss.systemsR 1 Reply Last reply
    0
    • ricci@discuss.systemsR ricci@discuss.systems

      This one is larger, physically (22.5 sq ft), than the first datacenter we looked it, but claims less power: 490kw. That's not a ton of power - my Chevy Bolt can draw 150kw from its batteries at max acceleration, and there are much bigger and sportier EVs that can draw something almost up in the range of this datacenter! (though only for brief periods of course! this datacenter probably draws a substantial fraction that much 24/7) Why is there so much less power for this datacenter?

      Well, one of the key factors of datacenters is how power-dense they are: how much power they are designed to deliver to each rack, and how much heat they are capable of moving out.

      Compute - especially GPU compute for AI - is incredibly power-dense and incredibly hot. So we can guess this datacenter is probably not for compute. If I had to guess, this is probably mainly intended as a "carrier hotel" - it's probably focused on having telecoms companies as tenants. I base this both on the lower power density, and where it is: it's near the Utah State Fairpark, which is in turn relatively close to train tracks heading both east-west and north-south. A lot of long-distance fiber in the US follows both the rail and Interstate road networks, because it's relatively straightforward to run fiber alongside transportation links. Salt Lake City lies on the west side of some of the few passes through the Rockies, so it has a ton of fiber, following I-80, the Union Pacific, etc. This is a good place for carrier hotels.

      How is a carrier hotel different from an IXP? At an IXP, the carrier is just pulling in some fiber, maybe one or two routers or something. But they have a lot more equipment that they need than that - they have servers of various kinds too, plus the bigger backbone routers that fan out in many directions, etc. Mobile carriers have a fair amount of wired topology to deal with. That's the kind of stuff they put in carrier hotels, and this is a good spot for them.

      I picked this shot because, in the background, you can see the Gadsby Power Plant, one of the main sources for power in #SLC. That's a natural gas plant that generates about 300MW. Put a pin in that number, we'll come back to it later.

      Link Preview Image
      ricci@discuss.systemsR This user is from outside of this forum
      ricci@discuss.systemsR This user is from outside of this forum
      ricci@discuss.systems
      wrote last edited by
      #4

      Now we're getting a bit bigger, and also more residential. This one sits on the edge of a residential neighborhood, on 200 E, in Milcreek. This is a 36k sq ft, 1.9 MW facility. What's in there? I don't know, as mentioned above, datacenters don't tend to tell you who their tenants are. There's probably some reasonable computing power in there, but it's probably not dense enough to be very GPU-heavy.

      The sounds of the HVAC systems were quite noticeable at this one. Any time you are dealing with electricity, you are also dealing with heat. In a datacenter, the power drawn by the compute and network equipment gets turned into heat, and you need to get rid of it. Of course, you want to spend as little electricity getting rid of heat as you can. Datacenters call this "Power Usage Effectiveness", commonly called PUE. A PUE of 1.5 means that for every KW that goes to computers, .5 KW goes to other stuff - mostly cooling, but also heat losses, lighting, etc. A 1.5 PUE is pretty good, supposedly some of the biggest datacenters have PUE of around 1.1 .

      This actually highlights one way in which having a fairly large-scale datacenter is efficient: putting all the computers in one place does enable you to use cooling systems that get rid of more heat for less power. Of course, how many computers you have, where your power is coming from, what mechanisms you use to cool them, etc. matters too! Again, we'll get back to that later.

      By the way, my guess would be that only the building in the front is a datacenter - the building in the back has too many truck bays and not enough cooling. It's probably a small warehouse of some sort.

      ricci@discuss.systemsR mjd@mathstodon.xyzM 2 Replies Last reply
      0
      • ricci@discuss.systemsR ricci@discuss.systems

        Now we're getting a bit bigger, and also more residential. This one sits on the edge of a residential neighborhood, on 200 E, in Milcreek. This is a 36k sq ft, 1.9 MW facility. What's in there? I don't know, as mentioned above, datacenters don't tend to tell you who their tenants are. There's probably some reasonable computing power in there, but it's probably not dense enough to be very GPU-heavy.

        The sounds of the HVAC systems were quite noticeable at this one. Any time you are dealing with electricity, you are also dealing with heat. In a datacenter, the power drawn by the compute and network equipment gets turned into heat, and you need to get rid of it. Of course, you want to spend as little electricity getting rid of heat as you can. Datacenters call this "Power Usage Effectiveness", commonly called PUE. A PUE of 1.5 means that for every KW that goes to computers, .5 KW goes to other stuff - mostly cooling, but also heat losses, lighting, etc. A 1.5 PUE is pretty good, supposedly some of the biggest datacenters have PUE of around 1.1 .

        This actually highlights one way in which having a fairly large-scale datacenter is efficient: putting all the computers in one place does enable you to use cooling systems that get rid of more heat for less power. Of course, how many computers you have, where your power is coming from, what mechanisms you use to cool them, etc. matters too! Again, we'll get back to that later.

        By the way, my guess would be that only the building in the front is a datacenter - the building in the back has too many truck bays and not enough cooling. It's probably a small warehouse of some sort.

        ricci@discuss.systemsR This user is from outside of this forum
        ricci@discuss.systemsR This user is from outside of this forum
        ricci@discuss.systems
        wrote last edited by
        #5

        This is the biggest datacenter I visited - campus, actually. This facility is in West Jordan, near the South Valley Regional Airport. It's big enough that I have to post several pictures to get you a real sense of the size (but it's not the biggest datacenter in Utah.)

        What you're looking at here is three buildings that, together, have a power capacity that's reported (depending on the source) to be around 160 MW (put a pin in that number too.)

        Two of these buildings are multi-tenant (the ones with the flat white roofs) like the others we've seen.

        That third one in the back, with all of the cooling towers on top, has supposedly been built for a single hyperscaler, and is supposedly something like an 80-100MW building. Which hyperscaler? That information is not public. That's a whole lot of cooling on the roof (which is reported to be water-free), so my money would be on this being an AI data center.

        In these pictures, you can see more electrical infrastructure. Bringing that much power into one place takes a lot of wires.

        Link Preview ImageLink Preview ImageLink Preview Image
        ricci@discuss.systemsR bnewbold@social.coopB 2 Replies Last reply
        0
        • ricci@discuss.systemsR ricci@discuss.systems

          This is the biggest datacenter I visited - campus, actually. This facility is in West Jordan, near the South Valley Regional Airport. It's big enough that I have to post several pictures to get you a real sense of the size (but it's not the biggest datacenter in Utah.)

          What you're looking at here is three buildings that, together, have a power capacity that's reported (depending on the source) to be around 160 MW (put a pin in that number too.)

          Two of these buildings are multi-tenant (the ones with the flat white roofs) like the others we've seen.

          That third one in the back, with all of the cooling towers on top, has supposedly been built for a single hyperscaler, and is supposedly something like an 80-100MW building. Which hyperscaler? That information is not public. That's a whole lot of cooling on the roof (which is reported to be water-free), so my money would be on this being an AI data center.

          In these pictures, you can see more electrical infrastructure. Bringing that much power into one place takes a lot of wires.

          Link Preview ImageLink Preview ImageLink Preview Image
          ricci@discuss.systemsR This user is from outside of this forum
          ricci@discuss.systemsR This user is from outside of this forum
          ricci@discuss.systems
          wrote last edited by
          #6

          The reason I went on this little tour was to put in perspective the proposed Stratos datacenter project in Box Elder County, UT.

          Stratos is supposedly designed to eventually reach a size of 9 GW. That is more than double the 4 GW that the entire state of Utah currently uses. The entire campus is supposed to be big enough that, for comparison, it would fill over 10% of the Salt Lake Valley, as shown in this image (which I didn't make).

          That last datacenter campus? At ~160 MW, those three buildings put together are designed for a load about 1/55th the size of Stratos. That 300 MW natural gas power station we saw in the background? Stratos is supposed to generate its own power on-site, so it will need 30 of those things. (Or maybe more - remember PUE?)

          In terms of carbon output, this thing is designed to be an absolute monster.

          There's not much getting around that. They have handwaved about including solar and/or wind, but without anything concrete, we should assume this is a whole lot of carbon.

          How about water?

          Well, that's harder to tell, given all the vagaries and "if"s in the public information so far.

          Remember, a datacenter has to get rid of a lot of heat. A datacenter that is generating its own energy on-site has to get rid of *far* more heat.

          In the desert West, the most *energy* efficient way of getting rid of heat in the hot summer months is evaporative cooling: you boil water. This has, historically, been a major way of cooling both natural gas plants and datacenters, as well as homes, etc.

          The same reason why this works well in the west is the same reason why it's problematic: we have very dry air, so evaporative cooling is very effective, but having dry air is connected to the fact that we don't have much water to begin with.

          There *are* ways to air-cool natural gas turbines, and there *are* ways to cool datacenters that are not evaporative cooling. They are more *water* efficient. But they are less *power* efficient, which means, in this context, burning even more natural gas.

          The backers of Stratos claim that they are trying to get some very new, high-tech gas turbines that operate without water cooling, or at least with very little. That does assuage some water concerns. But their language is very hedge-y - they're trying, they hope to jump in line for the limited supply of them, etc.

          They also claim they will use "closed loop" water systems for cooling the datacenter. There are several things this *could* mean, and we need to know more in order to actually understand it. Most cooling systems for datacenters and even large buildings have a closed loop of water (or another coolant) for moving heat around. That's because we cannot *make* cold, we can only *move* heat. In some datacenters, this cold loop comes into the room, where it's used to cool air, which is blown across the servers. In higher-power-density datacenters, the coolant loop comes all the way to the individual rack in order to cool the air right before it enters the servers. In the most high-tech datacenters (which Stratos would likely be), it comes all the way *inside* the server, directly exchanging heat with the hot bits like CPUs and GPUs.

          Coolant in these kinds of systems circulates, it's closed, you can generally consider the coolant loop to consume very little to no water after it's been filled.

          But: you still have to make the heat go away somehow. This is where Stratos *might* use evaporative cooling. Or they might opt for one of the more expensive, less energy efficient dry systems. Saying "we have a closed loop" only tells us *part* of the story!

          Here's what we know: the Stratos people have secured 13,000 acre-feet of water rights. In numbers that mean more to most of us, that's about 4 billion gallons per year.

          They *claim* that's far more water than they need, and they won't use most of it.

          But: if they don't manage to get their air-cooled gas turbines (which, in addition to being less efficient, also cost more), or decide to go with some evaporative cooling for the datacenter (because it's cheaper and uses less power), they could very easily use that much water. We are very much in a "trust me" situation, and it's not clear that we *should* trust what developers say when they are trying to get permits. We need to get independent studies and binding contracts.

          For those who aren't locals, you might not be aware, but: the Great Salt Lake is shrinking. People are trying (not hard enough, probably) to save it. Not just because hey, what would we call our city without it, but also because the lakebed is full of chemicals we'd rather not be breathing in, thanks.

          Stratos would not literally pull water out of the lake (which it is quite close to). But: the water rights they have obtained are in the watershed of the lake. So: if they use the water rights they have obtained, they might well contribute to the drying up of the lake.

          The point here is that: they are hoarding water rights that they claim they will not use - the more reasonable bet is to assume they will use them; we need a study by actual hydrologists to understand whether using the water would accelerate the lake's demise.

          And, you will notice that I have not even touched on a ton of *other* issues, such as:

          1) Is there actually demand for all of these computers?
          2) Would it be a good idea to fill this demand even if it does exist?
          3) Can we build enough computers to fill this thing in a reasonable time anyway?
          4) How far will this project get before the AI bubble pops, and will it leave anyone other than the investors holding the bag?
          5) If it does get fully built, what other resources (like more water rights) might they go after?
          6) Is it a wise idea to provide huge tax breaks to companies that expect to be highly profitable?
          7) This is being done though the Military Installation Development Authority - what's the actual military connection here?
          😎 Regardless of whether it's wet or dry, is dumping this much heat into one valley a good idea?
          9) There's no way that burning that much natural gas doesn't raise gas and electricity prices.
          10) Can we trust the developers' numbers for how many jobs this will create locally?

          Just to name a few.

          ricci@discuss.systemsR af@dataare.coolA mjd@mathstodon.xyzM grrrr_shark@supervolcano.angryshark.euG darwinwoodka@mastodon.socialD 15 Replies Last reply
          1
          0
          • ricci@discuss.systemsR ricci@discuss.systems

            The reason I went on this little tour was to put in perspective the proposed Stratos datacenter project in Box Elder County, UT.

            Stratos is supposedly designed to eventually reach a size of 9 GW. That is more than double the 4 GW that the entire state of Utah currently uses. The entire campus is supposed to be big enough that, for comparison, it would fill over 10% of the Salt Lake Valley, as shown in this image (which I didn't make).

            That last datacenter campus? At ~160 MW, those three buildings put together are designed for a load about 1/55th the size of Stratos. That 300 MW natural gas power station we saw in the background? Stratos is supposed to generate its own power on-site, so it will need 30 of those things. (Or maybe more - remember PUE?)

            In terms of carbon output, this thing is designed to be an absolute monster.

            There's not much getting around that. They have handwaved about including solar and/or wind, but without anything concrete, we should assume this is a whole lot of carbon.

            How about water?

            Well, that's harder to tell, given all the vagaries and "if"s in the public information so far.

            Remember, a datacenter has to get rid of a lot of heat. A datacenter that is generating its own energy on-site has to get rid of *far* more heat.

            In the desert West, the most *energy* efficient way of getting rid of heat in the hot summer months is evaporative cooling: you boil water. This has, historically, been a major way of cooling both natural gas plants and datacenters, as well as homes, etc.

            The same reason why this works well in the west is the same reason why it's problematic: we have very dry air, so evaporative cooling is very effective, but having dry air is connected to the fact that we don't have much water to begin with.

            There *are* ways to air-cool natural gas turbines, and there *are* ways to cool datacenters that are not evaporative cooling. They are more *water* efficient. But they are less *power* efficient, which means, in this context, burning even more natural gas.

            The backers of Stratos claim that they are trying to get some very new, high-tech gas turbines that operate without water cooling, or at least with very little. That does assuage some water concerns. But their language is very hedge-y - they're trying, they hope to jump in line for the limited supply of them, etc.

            They also claim they will use "closed loop" water systems for cooling the datacenter. There are several things this *could* mean, and we need to know more in order to actually understand it. Most cooling systems for datacenters and even large buildings have a closed loop of water (or another coolant) for moving heat around. That's because we cannot *make* cold, we can only *move* heat. In some datacenters, this cold loop comes into the room, where it's used to cool air, which is blown across the servers. In higher-power-density datacenters, the coolant loop comes all the way to the individual rack in order to cool the air right before it enters the servers. In the most high-tech datacenters (which Stratos would likely be), it comes all the way *inside* the server, directly exchanging heat with the hot bits like CPUs and GPUs.

            Coolant in these kinds of systems circulates, it's closed, you can generally consider the coolant loop to consume very little to no water after it's been filled.

            But: you still have to make the heat go away somehow. This is where Stratos *might* use evaporative cooling. Or they might opt for one of the more expensive, less energy efficient dry systems. Saying "we have a closed loop" only tells us *part* of the story!

            Here's what we know: the Stratos people have secured 13,000 acre-feet of water rights. In numbers that mean more to most of us, that's about 4 billion gallons per year.

            They *claim* that's far more water than they need, and they won't use most of it.

            But: if they don't manage to get their air-cooled gas turbines (which, in addition to being less efficient, also cost more), or decide to go with some evaporative cooling for the datacenter (because it's cheaper and uses less power), they could very easily use that much water. We are very much in a "trust me" situation, and it's not clear that we *should* trust what developers say when they are trying to get permits. We need to get independent studies and binding contracts.

            For those who aren't locals, you might not be aware, but: the Great Salt Lake is shrinking. People are trying (not hard enough, probably) to save it. Not just because hey, what would we call our city without it, but also because the lakebed is full of chemicals we'd rather not be breathing in, thanks.

            Stratos would not literally pull water out of the lake (which it is quite close to). But: the water rights they have obtained are in the watershed of the lake. So: if they use the water rights they have obtained, they might well contribute to the drying up of the lake.

            The point here is that: they are hoarding water rights that they claim they will not use - the more reasonable bet is to assume they will use them; we need a study by actual hydrologists to understand whether using the water would accelerate the lake's demise.

            And, you will notice that I have not even touched on a ton of *other* issues, such as:

            1) Is there actually demand for all of these computers?
            2) Would it be a good idea to fill this demand even if it does exist?
            3) Can we build enough computers to fill this thing in a reasonable time anyway?
            4) How far will this project get before the AI bubble pops, and will it leave anyone other than the investors holding the bag?
            5) If it does get fully built, what other resources (like more water rights) might they go after?
            6) Is it a wise idea to provide huge tax breaks to companies that expect to be highly profitable?
            7) This is being done though the Military Installation Development Authority - what's the actual military connection here?
            😎 Regardless of whether it's wet or dry, is dumping this much heat into one valley a good idea?
            9) There's no way that burning that much natural gas doesn't raise gas and electricity prices.
            10) Can we trust the developers' numbers for how many jobs this will create locally?

            Just to name a few.

            ricci@discuss.systemsR This user is from outside of this forum
            ricci@discuss.systemsR This user is from outside of this forum
            ricci@discuss.systems
            wrote last edited by
            #7

            Here's what I hope your takeaway from this thread will be: datacenters come in many sizes, have many uses, and are not necessarily where you'd expect. The impact they have locally depends on how they're powered, how they're cooled, what they're used for, who owns them, and how big they are. It's worth looking at all of these things when considering whether a datacenter project is a good idea or not.

            ericfielding@mastodon.socialE msbellows@c.imM gerbrandvd@mastodon.nlG phairupegiont@mastodon.socialP bnewbold@social.coopB 8 Replies Last reply
            0
            • ricci@discuss.systemsR ricci@discuss.systems

              Next, an even smaller datacenter, that just about anyone in #SLC has seen! This is XMission, a local Internet Service Provider that's been running since 1993, so one of The Ancients in Internet time. It's on a very busy part of 4th South, and if you've been by at night, you've seen the big LED display on the front of the building that they put various animations on.

              One of the things that I *think* is probably in this building is SLIX: https://slix.net/traffic/ - this is an Internet Exchange Point (IXP), where various carriers meet up to exchange traffic without it having to travel long distances. These are often run as a sort of community infrastructure - it's in the best interests of all networks involved to connect to each other so that they can do their jobs more efficiently.

              SLIX is fairly small (according to their own data they carry ~200Gbps, with some spikes up to 1Tbps). There are about 40 networks that meet there: https://slix.net/participants/ . Funny story, when I first got Google Fiber at my house, I was getting routed through California to get to the University of Utah campus just a few miles away. I pinged a guy I know who pinged a guy he knows who ... learned that some of the participants in SLIX didn't have their routes set up right. A config change later, and not only me, but basically everyone on any commercial ISP in the Salt Lake Valley had much more direct routes to campus!

              elb@social.sdf.orgE This user is from outside of this forum
              elb@social.sdf.orgE This user is from outside of this forum
              elb@social.sdf.org
              wrote last edited by
              #8

              @ricci Oh man, XMission ... I remember their domain from waaaaaayyyy back in the day, although to be honest I can no longer remember why. Something I went to a _lot_ was hosted there.

              ricci@discuss.systemsR 1 Reply Last reply
              0
              • elb@social.sdf.orgE elb@social.sdf.org

                @ricci Oh man, XMission ... I remember their domain from waaaaaayyyy back in the day, although to be honest I can no longer remember why. Something I went to a _lot_ was hosted there.

                ricci@discuss.systemsR This user is from outside of this forum
                ricci@discuss.systemsR This user is from outside of this forum
                ricci@discuss.systems
                wrote last edited by
                #9

                @elb Perhaps

                Link Preview Image
                The Best Page In The Universe.

                The Best Damn Web Page in the Universe

                favicon

                (maddox.xmission.com)

                ?

                elb@social.sdf.orgE 1 Reply Last reply
                0
                • ricci@discuss.systemsR ricci@discuss.systems

                  @elb Perhaps

                  Link Preview Image
                  The Best Page In The Universe.

                  The Best Damn Web Page in the Universe

                  favicon

                  (maddox.xmission.com)

                  ?

                  elb@social.sdf.orgE This user is from outside of this forum
                  elb@social.sdf.orgE This user is from outside of this forum
                  elb@social.sdf.org
                  wrote last edited by
                  #10

                  @ricci Uh yes that seems very likely.

                  1 Reply Last reply
                  0
                  • ricci@discuss.systemsR ricci@discuss.systems

                    The reason I went on this little tour was to put in perspective the proposed Stratos datacenter project in Box Elder County, UT.

                    Stratos is supposedly designed to eventually reach a size of 9 GW. That is more than double the 4 GW that the entire state of Utah currently uses. The entire campus is supposed to be big enough that, for comparison, it would fill over 10% of the Salt Lake Valley, as shown in this image (which I didn't make).

                    That last datacenter campus? At ~160 MW, those three buildings put together are designed for a load about 1/55th the size of Stratos. That 300 MW natural gas power station we saw in the background? Stratos is supposed to generate its own power on-site, so it will need 30 of those things. (Or maybe more - remember PUE?)

                    In terms of carbon output, this thing is designed to be an absolute monster.

                    There's not much getting around that. They have handwaved about including solar and/or wind, but without anything concrete, we should assume this is a whole lot of carbon.

                    How about water?

                    Well, that's harder to tell, given all the vagaries and "if"s in the public information so far.

                    Remember, a datacenter has to get rid of a lot of heat. A datacenter that is generating its own energy on-site has to get rid of *far* more heat.

                    In the desert West, the most *energy* efficient way of getting rid of heat in the hot summer months is evaporative cooling: you boil water. This has, historically, been a major way of cooling both natural gas plants and datacenters, as well as homes, etc.

                    The same reason why this works well in the west is the same reason why it's problematic: we have very dry air, so evaporative cooling is very effective, but having dry air is connected to the fact that we don't have much water to begin with.

                    There *are* ways to air-cool natural gas turbines, and there *are* ways to cool datacenters that are not evaporative cooling. They are more *water* efficient. But they are less *power* efficient, which means, in this context, burning even more natural gas.

                    The backers of Stratos claim that they are trying to get some very new, high-tech gas turbines that operate without water cooling, or at least with very little. That does assuage some water concerns. But their language is very hedge-y - they're trying, they hope to jump in line for the limited supply of them, etc.

                    They also claim they will use "closed loop" water systems for cooling the datacenter. There are several things this *could* mean, and we need to know more in order to actually understand it. Most cooling systems for datacenters and even large buildings have a closed loop of water (or another coolant) for moving heat around. That's because we cannot *make* cold, we can only *move* heat. In some datacenters, this cold loop comes into the room, where it's used to cool air, which is blown across the servers. In higher-power-density datacenters, the coolant loop comes all the way to the individual rack in order to cool the air right before it enters the servers. In the most high-tech datacenters (which Stratos would likely be), it comes all the way *inside* the server, directly exchanging heat with the hot bits like CPUs and GPUs.

                    Coolant in these kinds of systems circulates, it's closed, you can generally consider the coolant loop to consume very little to no water after it's been filled.

                    But: you still have to make the heat go away somehow. This is where Stratos *might* use evaporative cooling. Or they might opt for one of the more expensive, less energy efficient dry systems. Saying "we have a closed loop" only tells us *part* of the story!

                    Here's what we know: the Stratos people have secured 13,000 acre-feet of water rights. In numbers that mean more to most of us, that's about 4 billion gallons per year.

                    They *claim* that's far more water than they need, and they won't use most of it.

                    But: if they don't manage to get their air-cooled gas turbines (which, in addition to being less efficient, also cost more), or decide to go with some evaporative cooling for the datacenter (because it's cheaper and uses less power), they could very easily use that much water. We are very much in a "trust me" situation, and it's not clear that we *should* trust what developers say when they are trying to get permits. We need to get independent studies and binding contracts.

                    For those who aren't locals, you might not be aware, but: the Great Salt Lake is shrinking. People are trying (not hard enough, probably) to save it. Not just because hey, what would we call our city without it, but also because the lakebed is full of chemicals we'd rather not be breathing in, thanks.

                    Stratos would not literally pull water out of the lake (which it is quite close to). But: the water rights they have obtained are in the watershed of the lake. So: if they use the water rights they have obtained, they might well contribute to the drying up of the lake.

                    The point here is that: they are hoarding water rights that they claim they will not use - the more reasonable bet is to assume they will use them; we need a study by actual hydrologists to understand whether using the water would accelerate the lake's demise.

                    And, you will notice that I have not even touched on a ton of *other* issues, such as:

                    1) Is there actually demand for all of these computers?
                    2) Would it be a good idea to fill this demand even if it does exist?
                    3) Can we build enough computers to fill this thing in a reasonable time anyway?
                    4) How far will this project get before the AI bubble pops, and will it leave anyone other than the investors holding the bag?
                    5) If it does get fully built, what other resources (like more water rights) might they go after?
                    6) Is it a wise idea to provide huge tax breaks to companies that expect to be highly profitable?
                    7) This is being done though the Military Installation Development Authority - what's the actual military connection here?
                    😎 Regardless of whether it's wet or dry, is dumping this much heat into one valley a good idea?
                    9) There's no way that burning that much natural gas doesn't raise gas and electricity prices.
                    10) Can we trust the developers' numbers for how many jobs this will create locally?

                    Just to name a few.

                    af@dataare.coolA This user is from outside of this forum
                    af@dataare.coolA This user is from outside of this forum
                    af@dataare.cool
                    wrote last edited by
                    #11

                    @ricci Jesus H Christ that’s massive. I’ve always objected to the « water use » reservations regarding data centres, but purely from a UK perspective where:

                    a) onsite generation is generally a no-no
                    b) evaporative cooling isn’t required, and generally a no-no

                    This hits home the difference in planning and land use regulations between the UK and US. This would never be considered here.

                    ricci@discuss.systemsR 1 Reply Last reply
                    0
                    • ricci@discuss.systemsR ricci@discuss.systems

                      Here's what I hope your takeaway from this thread will be: datacenters come in many sizes, have many uses, and are not necessarily where you'd expect. The impact they have locally depends on how they're powered, how they're cooled, what they're used for, who owns them, and how big they are. It's worth looking at all of these things when considering whether a datacenter project is a good idea or not.

                      ericfielding@mastodon.socialE This user is from outside of this forum
                      ericfielding@mastodon.socialE This user is from outside of this forum
                      ericfielding@mastodon.social
                      wrote last edited by
                      #12

                      @ricci Thanks for the detailed description. I saw something about the residents trying to fight this but didn’t know the crazy scale.

                      ricci@discuss.systemsR 1 Reply Last reply
                      0
                      • af@dataare.coolA af@dataare.cool

                        @ricci Jesus H Christ that’s massive. I’ve always objected to the « water use » reservations regarding data centres, but purely from a UK perspective where:

                        a) onsite generation is generally a no-no
                        b) evaporative cooling isn’t required, and generally a no-no

                        This hits home the difference in planning and land use regulations between the UK and US. This would never be considered here.

                        ricci@discuss.systemsR This user is from outside of this forum
                        ricci@discuss.systemsR This user is from outside of this forum
                        ricci@discuss.systems
                        wrote last edited by
                        #13

                        @af

                        Yes, this is absolutely massive.

                        As far as on-site generation goes, this is *sort* of in the kind of area where one might built a power plant in the first place, it's pretty remote. So I think the issues have more to do with carbon emissions, the heat load in a high-desert valley, and the scale than with the fact that it's on site per se.

                        Evaporative cooling is *much* more effective here where our humidity is basically a rounding error away from zero. But yeah, we are very much out of water, and we need to not take the developers word for it that they don't intend to use it.

                        1 Reply Last reply
                        0
                        • ricci@discuss.systemsR ricci@discuss.systems

                          The reason I went on this little tour was to put in perspective the proposed Stratos datacenter project in Box Elder County, UT.

                          Stratos is supposedly designed to eventually reach a size of 9 GW. That is more than double the 4 GW that the entire state of Utah currently uses. The entire campus is supposed to be big enough that, for comparison, it would fill over 10% of the Salt Lake Valley, as shown in this image (which I didn't make).

                          That last datacenter campus? At ~160 MW, those three buildings put together are designed for a load about 1/55th the size of Stratos. That 300 MW natural gas power station we saw in the background? Stratos is supposed to generate its own power on-site, so it will need 30 of those things. (Or maybe more - remember PUE?)

                          In terms of carbon output, this thing is designed to be an absolute monster.

                          There's not much getting around that. They have handwaved about including solar and/or wind, but without anything concrete, we should assume this is a whole lot of carbon.

                          How about water?

                          Well, that's harder to tell, given all the vagaries and "if"s in the public information so far.

                          Remember, a datacenter has to get rid of a lot of heat. A datacenter that is generating its own energy on-site has to get rid of *far* more heat.

                          In the desert West, the most *energy* efficient way of getting rid of heat in the hot summer months is evaporative cooling: you boil water. This has, historically, been a major way of cooling both natural gas plants and datacenters, as well as homes, etc.

                          The same reason why this works well in the west is the same reason why it's problematic: we have very dry air, so evaporative cooling is very effective, but having dry air is connected to the fact that we don't have much water to begin with.

                          There *are* ways to air-cool natural gas turbines, and there *are* ways to cool datacenters that are not evaporative cooling. They are more *water* efficient. But they are less *power* efficient, which means, in this context, burning even more natural gas.

                          The backers of Stratos claim that they are trying to get some very new, high-tech gas turbines that operate without water cooling, or at least with very little. That does assuage some water concerns. But their language is very hedge-y - they're trying, they hope to jump in line for the limited supply of them, etc.

                          They also claim they will use "closed loop" water systems for cooling the datacenter. There are several things this *could* mean, and we need to know more in order to actually understand it. Most cooling systems for datacenters and even large buildings have a closed loop of water (or another coolant) for moving heat around. That's because we cannot *make* cold, we can only *move* heat. In some datacenters, this cold loop comes into the room, where it's used to cool air, which is blown across the servers. In higher-power-density datacenters, the coolant loop comes all the way to the individual rack in order to cool the air right before it enters the servers. In the most high-tech datacenters (which Stratos would likely be), it comes all the way *inside* the server, directly exchanging heat with the hot bits like CPUs and GPUs.

                          Coolant in these kinds of systems circulates, it's closed, you can generally consider the coolant loop to consume very little to no water after it's been filled.

                          But: you still have to make the heat go away somehow. This is where Stratos *might* use evaporative cooling. Or they might opt for one of the more expensive, less energy efficient dry systems. Saying "we have a closed loop" only tells us *part* of the story!

                          Here's what we know: the Stratos people have secured 13,000 acre-feet of water rights. In numbers that mean more to most of us, that's about 4 billion gallons per year.

                          They *claim* that's far more water than they need, and they won't use most of it.

                          But: if they don't manage to get their air-cooled gas turbines (which, in addition to being less efficient, also cost more), or decide to go with some evaporative cooling for the datacenter (because it's cheaper and uses less power), they could very easily use that much water. We are very much in a "trust me" situation, and it's not clear that we *should* trust what developers say when they are trying to get permits. We need to get independent studies and binding contracts.

                          For those who aren't locals, you might not be aware, but: the Great Salt Lake is shrinking. People are trying (not hard enough, probably) to save it. Not just because hey, what would we call our city without it, but also because the lakebed is full of chemicals we'd rather not be breathing in, thanks.

                          Stratos would not literally pull water out of the lake (which it is quite close to). But: the water rights they have obtained are in the watershed of the lake. So: if they use the water rights they have obtained, they might well contribute to the drying up of the lake.

                          The point here is that: they are hoarding water rights that they claim they will not use - the more reasonable bet is to assume they will use them; we need a study by actual hydrologists to understand whether using the water would accelerate the lake's demise.

                          And, you will notice that I have not even touched on a ton of *other* issues, such as:

                          1) Is there actually demand for all of these computers?
                          2) Would it be a good idea to fill this demand even if it does exist?
                          3) Can we build enough computers to fill this thing in a reasonable time anyway?
                          4) How far will this project get before the AI bubble pops, and will it leave anyone other than the investors holding the bag?
                          5) If it does get fully built, what other resources (like more water rights) might they go after?
                          6) Is it a wise idea to provide huge tax breaks to companies that expect to be highly profitable?
                          7) This is being done though the Military Installation Development Authority - what's the actual military connection here?
                          😎 Regardless of whether it's wet or dry, is dumping this much heat into one valley a good idea?
                          9) There's no way that burning that much natural gas doesn't raise gas and electricity prices.
                          10) Can we trust the developers' numbers for how many jobs this will create locally?

                          Just to name a few.

                          mjd@mathstodon.xyzM This user is from outside of this forum
                          mjd@mathstodon.xyzM This user is from outside of this forum
                          mjd@mathstodon.xyz
                          wrote last edited by
                          #14

                          @ricci Thanks so much for putting this together.

                          1 Reply Last reply
                          0
                          • ericfielding@mastodon.socialE ericfielding@mastodon.social

                            @ricci Thanks for the detailed description. I saw something about the residents trying to fight this but didn’t know the crazy scale.

                            ricci@discuss.systemsR This user is from outside of this forum
                            ricci@discuss.systemsR This user is from outside of this forum
                            ricci@discuss.systems
                            wrote last edited by
                            #15

                            @EricFielding Also, a thing I didn't mention is that this is not the only datacenter of this size being proposed in the state. There's another one just as big being discussed for central Utah.

                            1 Reply Last reply
                            0
                            • ricci@discuss.systemsR ricci@discuss.systems

                              The reason I went on this little tour was to put in perspective the proposed Stratos datacenter project in Box Elder County, UT.

                              Stratos is supposedly designed to eventually reach a size of 9 GW. That is more than double the 4 GW that the entire state of Utah currently uses. The entire campus is supposed to be big enough that, for comparison, it would fill over 10% of the Salt Lake Valley, as shown in this image (which I didn't make).

                              That last datacenter campus? At ~160 MW, those three buildings put together are designed for a load about 1/55th the size of Stratos. That 300 MW natural gas power station we saw in the background? Stratos is supposed to generate its own power on-site, so it will need 30 of those things. (Or maybe more - remember PUE?)

                              In terms of carbon output, this thing is designed to be an absolute monster.

                              There's not much getting around that. They have handwaved about including solar and/or wind, but without anything concrete, we should assume this is a whole lot of carbon.

                              How about water?

                              Well, that's harder to tell, given all the vagaries and "if"s in the public information so far.

                              Remember, a datacenter has to get rid of a lot of heat. A datacenter that is generating its own energy on-site has to get rid of *far* more heat.

                              In the desert West, the most *energy* efficient way of getting rid of heat in the hot summer months is evaporative cooling: you boil water. This has, historically, been a major way of cooling both natural gas plants and datacenters, as well as homes, etc.

                              The same reason why this works well in the west is the same reason why it's problematic: we have very dry air, so evaporative cooling is very effective, but having dry air is connected to the fact that we don't have much water to begin with.

                              There *are* ways to air-cool natural gas turbines, and there *are* ways to cool datacenters that are not evaporative cooling. They are more *water* efficient. But they are less *power* efficient, which means, in this context, burning even more natural gas.

                              The backers of Stratos claim that they are trying to get some very new, high-tech gas turbines that operate without water cooling, or at least with very little. That does assuage some water concerns. But their language is very hedge-y - they're trying, they hope to jump in line for the limited supply of them, etc.

                              They also claim they will use "closed loop" water systems for cooling the datacenter. There are several things this *could* mean, and we need to know more in order to actually understand it. Most cooling systems for datacenters and even large buildings have a closed loop of water (or another coolant) for moving heat around. That's because we cannot *make* cold, we can only *move* heat. In some datacenters, this cold loop comes into the room, where it's used to cool air, which is blown across the servers. In higher-power-density datacenters, the coolant loop comes all the way to the individual rack in order to cool the air right before it enters the servers. In the most high-tech datacenters (which Stratos would likely be), it comes all the way *inside* the server, directly exchanging heat with the hot bits like CPUs and GPUs.

                              Coolant in these kinds of systems circulates, it's closed, you can generally consider the coolant loop to consume very little to no water after it's been filled.

                              But: you still have to make the heat go away somehow. This is where Stratos *might* use evaporative cooling. Or they might opt for one of the more expensive, less energy efficient dry systems. Saying "we have a closed loop" only tells us *part* of the story!

                              Here's what we know: the Stratos people have secured 13,000 acre-feet of water rights. In numbers that mean more to most of us, that's about 4 billion gallons per year.

                              They *claim* that's far more water than they need, and they won't use most of it.

                              But: if they don't manage to get their air-cooled gas turbines (which, in addition to being less efficient, also cost more), or decide to go with some evaporative cooling for the datacenter (because it's cheaper and uses less power), they could very easily use that much water. We are very much in a "trust me" situation, and it's not clear that we *should* trust what developers say when they are trying to get permits. We need to get independent studies and binding contracts.

                              For those who aren't locals, you might not be aware, but: the Great Salt Lake is shrinking. People are trying (not hard enough, probably) to save it. Not just because hey, what would we call our city without it, but also because the lakebed is full of chemicals we'd rather not be breathing in, thanks.

                              Stratos would not literally pull water out of the lake (which it is quite close to). But: the water rights they have obtained are in the watershed of the lake. So: if they use the water rights they have obtained, they might well contribute to the drying up of the lake.

                              The point here is that: they are hoarding water rights that they claim they will not use - the more reasonable bet is to assume they will use them; we need a study by actual hydrologists to understand whether using the water would accelerate the lake's demise.

                              And, you will notice that I have not even touched on a ton of *other* issues, such as:

                              1) Is there actually demand for all of these computers?
                              2) Would it be a good idea to fill this demand even if it does exist?
                              3) Can we build enough computers to fill this thing in a reasonable time anyway?
                              4) How far will this project get before the AI bubble pops, and will it leave anyone other than the investors holding the bag?
                              5) If it does get fully built, what other resources (like more water rights) might they go after?
                              6) Is it a wise idea to provide huge tax breaks to companies that expect to be highly profitable?
                              7) This is being done though the Military Installation Development Authority - what's the actual military connection here?
                              😎 Regardless of whether it's wet or dry, is dumping this much heat into one valley a good idea?
                              9) There's no way that burning that much natural gas doesn't raise gas and electricity prices.
                              10) Can we trust the developers' numbers for how many jobs this will create locally?

                              Just to name a few.

                              grrrr_shark@supervolcano.angryshark.euG This user is from outside of this forum
                              grrrr_shark@supervolcano.angryshark.euG This user is from outside of this forum
                              grrrr_shark@supervolcano.angryshark.eu
                              wrote last edited by
                              #16

                              @ricci Christ. I lived in SLC in the early 70s. Droughts etc etc. And that was with less population and...

                              I hate everything right now,

                              1 Reply Last reply
                              0
                              • ricci@discuss.systemsR ricci@discuss.systems

                                Now we're getting a bit bigger, and also more residential. This one sits on the edge of a residential neighborhood, on 200 E, in Milcreek. This is a 36k sq ft, 1.9 MW facility. What's in there? I don't know, as mentioned above, datacenters don't tend to tell you who their tenants are. There's probably some reasonable computing power in there, but it's probably not dense enough to be very GPU-heavy.

                                The sounds of the HVAC systems were quite noticeable at this one. Any time you are dealing with electricity, you are also dealing with heat. In a datacenter, the power drawn by the compute and network equipment gets turned into heat, and you need to get rid of it. Of course, you want to spend as little electricity getting rid of heat as you can. Datacenters call this "Power Usage Effectiveness", commonly called PUE. A PUE of 1.5 means that for every KW that goes to computers, .5 KW goes to other stuff - mostly cooling, but also heat losses, lighting, etc. A 1.5 PUE is pretty good, supposedly some of the biggest datacenters have PUE of around 1.1 .

                                This actually highlights one way in which having a fairly large-scale datacenter is efficient: putting all the computers in one place does enable you to use cooling systems that get rid of more heat for less power. Of course, how many computers you have, where your power is coming from, what mechanisms you use to cool them, etc. matters too! Again, we'll get back to that later.

                                By the way, my guess would be that only the building in the front is a datacenter - the building in the back has too many truck bays and not enough cooling. It's probably a small warehouse of some sort.

                                mjd@mathstodon.xyzM This user is from outside of this forum
                                mjd@mathstodon.xyzM This user is from outside of this forum
                                mjd@mathstodon.xyz
                                wrote last edited by
                                #17

                                @ricci How do you find out the size and power usage of a particular data center?

                                ricci@discuss.systemsR 1 Reply Last reply
                                0
                                • mjd@mathstodon.xyzM mjd@mathstodon.xyz

                                  @ricci How do you find out the size and power usage of a particular data center?

                                  ricci@discuss.systemsR This user is from outside of this forum
                                  ricci@discuss.systemsR This user is from outside of this forum
                                  ricci@discuss.systems
                                  wrote last edited by
                                  #18

                                  @mjd

                                  Excellent question! For the mutlt-tenant datacenters, location, size, and power draw is generally advertised, because they are trying to attract customers. I pulled it from datacentermap.com, so, for example:

                                  Vercel Security Checkpoint

                                  favicon

                                  (www.datacentermap.com)

                                  For the private ones, like the likely-AI building at this campus, you mostly have to get this information from press releases. So it's probably less reliable, as there is more incentive to overhype.

                                  mjd@mathstodon.xyzM 1 Reply Last reply
                                  0
                                  • ricci@discuss.systemsR ricci@discuss.systems

                                    @mjd

                                    Excellent question! For the mutlt-tenant datacenters, location, size, and power draw is generally advertised, because they are trying to attract customers. I pulled it from datacentermap.com, so, for example:

                                    Vercel Security Checkpoint

                                    favicon

                                    (www.datacentermap.com)

                                    For the private ones, like the likely-AI building at this campus, you mostly have to get this information from press releases. So it's probably less reliable, as there is more incentive to overhype.

                                    mjd@mathstodon.xyzM This user is from outside of this forum
                                    mjd@mathstodon.xyzM This user is from outside of this forum
                                    mjd@mathstodon.xyz
                                    wrote last edited by
                                    #19

                                    @ricci Thanks!

                                    When I saw the claim about the 9GW data center, my immediate thought was that it was simply a lie, intended as an advertisement to potential investors: Look what amazing stuff we are going to do!

                                    How plausible do you find the claim that they actually intend to build a 9GW data center that will take up 10% of the Salt Lake Valley?

                                    ricci@discuss.systemsR 1 Reply Last reply
                                    0
                                    • mjd@mathstodon.xyzM mjd@mathstodon.xyz

                                      @ricci Thanks!

                                      When I saw the claim about the 9GW data center, my immediate thought was that it was simply a lie, intended as an advertisement to potential investors: Look what amazing stuff we are going to do!

                                      How plausible do you find the claim that they actually intend to build a 9GW data center that will take up 10% of the Salt Lake Valley?

                                      ricci@discuss.systemsR This user is from outside of this forum
                                      ricci@discuss.systemsR This user is from outside of this forum
                                      ricci@discuss.systems
                                      wrote last edited by
                                      #20

                                      @mjd Frankly, I think it's entirely implausible that it will get built as advertised. I'm not sure that the demand is actually there for as many datacenter projects as have been announced. I think it's a very good bet that many or even most of them won't get built out to the size they've discussed. I think the game here is to make big announcements to try to grab headlines and capital before someone else does, and before demand collapses. Is this one of the ones that might actually get built? No idea.

                                      One likely pivot, if the datacenter doesn't get built, or gets built at a much smaller size, is that they switch to being a private power plant with a bunch of land where they don't have to follow state or county land-use regulations (this is what MIDA is for). That would likely mean bringing in other energy-intensive industries; they have more or less said this in county commission meetings. There's a chance that this is actually far worse, as datacenters (if they use low-water cooling) actually use less water and don't produce as much ground pollution as many industrial land uses.

                                      skybrian@mastodon.socialS 1 Reply Last reply
                                      0
                                      • ricci@discuss.systemsR ricci@discuss.systems

                                        The reason I went on this little tour was to put in perspective the proposed Stratos datacenter project in Box Elder County, UT.

                                        Stratos is supposedly designed to eventually reach a size of 9 GW. That is more than double the 4 GW that the entire state of Utah currently uses. The entire campus is supposed to be big enough that, for comparison, it would fill over 10% of the Salt Lake Valley, as shown in this image (which I didn't make).

                                        That last datacenter campus? At ~160 MW, those three buildings put together are designed for a load about 1/55th the size of Stratos. That 300 MW natural gas power station we saw in the background? Stratos is supposed to generate its own power on-site, so it will need 30 of those things. (Or maybe more - remember PUE?)

                                        In terms of carbon output, this thing is designed to be an absolute monster.

                                        There's not much getting around that. They have handwaved about including solar and/or wind, but without anything concrete, we should assume this is a whole lot of carbon.

                                        How about water?

                                        Well, that's harder to tell, given all the vagaries and "if"s in the public information so far.

                                        Remember, a datacenter has to get rid of a lot of heat. A datacenter that is generating its own energy on-site has to get rid of *far* more heat.

                                        In the desert West, the most *energy* efficient way of getting rid of heat in the hot summer months is evaporative cooling: you boil water. This has, historically, been a major way of cooling both natural gas plants and datacenters, as well as homes, etc.

                                        The same reason why this works well in the west is the same reason why it's problematic: we have very dry air, so evaporative cooling is very effective, but having dry air is connected to the fact that we don't have much water to begin with.

                                        There *are* ways to air-cool natural gas turbines, and there *are* ways to cool datacenters that are not evaporative cooling. They are more *water* efficient. But they are less *power* efficient, which means, in this context, burning even more natural gas.

                                        The backers of Stratos claim that they are trying to get some very new, high-tech gas turbines that operate without water cooling, or at least with very little. That does assuage some water concerns. But their language is very hedge-y - they're trying, they hope to jump in line for the limited supply of them, etc.

                                        They also claim they will use "closed loop" water systems for cooling the datacenter. There are several things this *could* mean, and we need to know more in order to actually understand it. Most cooling systems for datacenters and even large buildings have a closed loop of water (or another coolant) for moving heat around. That's because we cannot *make* cold, we can only *move* heat. In some datacenters, this cold loop comes into the room, where it's used to cool air, which is blown across the servers. In higher-power-density datacenters, the coolant loop comes all the way to the individual rack in order to cool the air right before it enters the servers. In the most high-tech datacenters (which Stratos would likely be), it comes all the way *inside* the server, directly exchanging heat with the hot bits like CPUs and GPUs.

                                        Coolant in these kinds of systems circulates, it's closed, you can generally consider the coolant loop to consume very little to no water after it's been filled.

                                        But: you still have to make the heat go away somehow. This is where Stratos *might* use evaporative cooling. Or they might opt for one of the more expensive, less energy efficient dry systems. Saying "we have a closed loop" only tells us *part* of the story!

                                        Here's what we know: the Stratos people have secured 13,000 acre-feet of water rights. In numbers that mean more to most of us, that's about 4 billion gallons per year.

                                        They *claim* that's far more water than they need, and they won't use most of it.

                                        But: if they don't manage to get their air-cooled gas turbines (which, in addition to being less efficient, also cost more), or decide to go with some evaporative cooling for the datacenter (because it's cheaper and uses less power), they could very easily use that much water. We are very much in a "trust me" situation, and it's not clear that we *should* trust what developers say when they are trying to get permits. We need to get independent studies and binding contracts.

                                        For those who aren't locals, you might not be aware, but: the Great Salt Lake is shrinking. People are trying (not hard enough, probably) to save it. Not just because hey, what would we call our city without it, but also because the lakebed is full of chemicals we'd rather not be breathing in, thanks.

                                        Stratos would not literally pull water out of the lake (which it is quite close to). But: the water rights they have obtained are in the watershed of the lake. So: if they use the water rights they have obtained, they might well contribute to the drying up of the lake.

                                        The point here is that: they are hoarding water rights that they claim they will not use - the more reasonable bet is to assume they will use them; we need a study by actual hydrologists to understand whether using the water would accelerate the lake's demise.

                                        And, you will notice that I have not even touched on a ton of *other* issues, such as:

                                        1) Is there actually demand for all of these computers?
                                        2) Would it be a good idea to fill this demand even if it does exist?
                                        3) Can we build enough computers to fill this thing in a reasonable time anyway?
                                        4) How far will this project get before the AI bubble pops, and will it leave anyone other than the investors holding the bag?
                                        5) If it does get fully built, what other resources (like more water rights) might they go after?
                                        6) Is it a wise idea to provide huge tax breaks to companies that expect to be highly profitable?
                                        7) This is being done though the Military Installation Development Authority - what's the actual military connection here?
                                        😎 Regardless of whether it's wet or dry, is dumping this much heat into one valley a good idea?
                                        9) There's no way that burning that much natural gas doesn't raise gas and electricity prices.
                                        10) Can we trust the developers' numbers for how many jobs this will create locally?

                                        Just to name a few.

                                        darwinwoodka@mastodon.socialD This user is from outside of this forum
                                        darwinwoodka@mastodon.socialD This user is from outside of this forum
                                        darwinwoodka@mastodon.social
                                        wrote last edited by
                                        #21

                                        @ricci

                                        Why are we building housing for computers and not for people?

                                        ricci@discuss.systemsR jonhendry@iosdev.spaceJ 2 Replies Last reply
                                        0
                                        • darwinwoodka@mastodon.socialD darwinwoodka@mastodon.social

                                          @ricci

                                          Why are we building housing for computers and not for people?

                                          ricci@discuss.systemsR This user is from outside of this forum
                                          ricci@discuss.systemsR This user is from outside of this forum
                                          ricci@discuss.systems
                                          wrote last edited by
                                          #22

                                          @darwinwoodka just imagine what we could do if we put these kinds of resources to other uses

                                          1 Reply Last reply
                                          0
                                          Reply
                                          • Reply as topic
                                          Log in to reply
                                          • Oldest to Newest
                                          • Newest to Oldest
                                          • Most Votes


                                          • Login

                                          • Login or register to search.
                                          • First post
                                            Last post
                                          0
                                          • Categories
                                          • Recent
                                          • Tags
                                          • Popular
                                          • World
                                          • Users
                                          • Groups